Module 2 : Project Planning
AOA and AON Networks

FLOATS Computations : Activity ' h '


- Total Float = LS - ES = LF - EF =2
- Safety float = Total Float - [Max (LF of predecessors)-ES] = 2- (12 - 12) = 2
- Free float = Total Float -[LF -Min(ES of successors)] = 2 - (18 - 18) = 2
- Independent float = Total float - both the latter terms = 2 - (0+0) = 2